(Lindenwold, NJ) – Several roadway projects will be underway across Camden County during the week of November 16 to November 20. 

“Motorists should plan ahead to take alternate routes and give themselves plenty of time to get to their destinations,” said Commissioner Al Dyer, liaison to the Department of Public Works. “Also, remember that when you’re traveling through a construction area, please slow down and stay alert for crew members and debris.”

Audubon

·         Crews will be working on East Atlantic Avenue from Monday, November 16, to Friday, November 20, from 7:00 a.m. to 5:30 p.m. There will be a lane closure between West Merchant Street in Audubon and Station Avenue in Haddon Heights.

·         Crews will be working on Kings Highway on Monday, November 16, to Friday, November 20, from 9:00 a.m. to 2:00 p.m. There will be a moving operation using shoulder closures between 10th Avenue in Audubon and St. Martins Avenue in Haddon Heights.

Camden

·         PSE&G will be working on Ferry Avenue on Wednesday, November 18, to Friday. November 20, from 7:00 a.m. to 4:00 p.m. There will be a lane shift and sidewalk closures between Mechanic Street & Liberty Street. 

·         PSE&G will be working on Kaighn Avenue on Tuesday, November 17, and Wednesday, November 18, from 7:30 a.m. to 4:00 p.m. There will be a lane shift at the intersection with Vesper Boulevard. 

·         Crews will be working on Haddon Avenue on Monday, November 16, to Friday, November 20, from 9:30 a.m. to 3:30 p.m. There will be a northbound shoulder closure at the intersection with Dr. Martin Luther King Jr. Boulevard.

·         Crews will be working on River Avenue from Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:00 p.m. There will be a full road closure between Federal Street and the Conrail Railroad tracks:

·         Crews will be working on Newton Avenue from Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:30 p.m. There will be a full road closure between Broadway and South 7th Street.

·         PSE&G will be working on 1313 Mt. Ephraim Avenue from Monday, November 16, to Friday, November 20, from 9:00 a.m. to 2:00 p.m. There will be a lane shift and sidewalk closures between Mechanic Street & Liberty Street. 

Cherry Hill

Crews will be working on Evesham Road on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:30 p.m. There will be partial road closures between Haddonfield-Berlin Road in Cherry Hill and Burnt Mill Road in Voorhees.

Clementon

Crews will be working on White Horse Avenue from Monday, November 16, to Friday, November 20, from 7:00 a.m. to 4:00 p.m. On Monday and Tuesday, there will be a partial eastbound road closure between Gibbsboro Road in Clementon and White Horse Pike in Lindenwold. From Wednesday to Friday, there will be a full road closure between Gibbsboro Road in Clementon and White Horse Pike in Lindenwold. 

Gloucester Township

·         Crews will be working on Evesham Road on Monday, November 16, to Thursday, November 19, from 6:30 p.m. to 6:00 a.m. (Monday to Wednesday), and 7:00 a.m. to 3:00 p.m. ( Tuesday to Friday) There will be a full road closure between Black Horse Pike in Gloucester Township and West Clements Bridge Road (Route 41) in Runnemede.

·         Crews will be working on Somerdale Road on Monday, November 9, to Friday, November 13, from 7:00 p.m. to 5:00 a.m. There will be a lane shift and sidewalk closures between Chews Landing Road and Lamppost Lane.

Haddon Heights

·         Crews will be working on East Atlantic Avenue from Monday, November 16, to Friday, November 20, from 7:00 a.m. to 5:30 p.m. There will be a lane closure between West Merchant Street in Audubon and Station Avenue in Haddon Heights.

·         Verizon will be working on Kings Highway on Monday, November 16, to Friday, November 20, from 9:00 a,m, to 2:00 p.m. There will be a moving operation using shoulder closures between 10th Avenue in Audubon and St. Martins Avenue in Haddon Heights.

Haddon Township

Crews will be working on Haddon Avenue on Monday, November 16, to Wednesday, November 18, from 7:00 a.m. to 4:00 p.m. There will be lane closures/shifts between West Cuthbert Boulevard and Strawbridge Avenue.

Lindenwold

·         Crews will be working on White Horse Avenue on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 4:00 p.m. On Monday and Tuesday, there will be a partial eastbound road closure between Gibbsboro Road in Clementon and White Horse Pike in Lindenwold. From Wednesday to Friday, there will be a full road closure between Gibbsboro Road in Clementon and White Horse Pike in Lindenwold. 

·         South Jersey Gas will be working on Laurel Road on Monday, November 16, and Tuesday, November 17, from 7:00 a.m. to 5:00 p.m. There will be a partial southbound road closure between Chews Landing Road and Blackwood-Clementon Road.

Magnolia

South Jersey Gas will be working on Evesham Road on Wednesday, November 18, from 9:00 a.m. to 3:00 p.m. There will be a full road closure between North Walnut Avenue and Atlantic Avenue.

Oaklyn

PSE&G will be working on Kendall Boulevard on Thursday, November 19, and Friday, November 20, from 7:00 a.m. to 5:00 p.m. There will be a full road closure between Congress Avenue and Landis Avenue. 

Pennsauken

Crews will be working on River Road on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:00 p.m. There will be a shoulder closure between North 36th Street and Delair Avenue.

Pine Hill

  • Crews will be working on West Branch Avenue on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:30 p.m. There will be a full road closure between Blackwood-Clementon Road and Erial Road.
  • Crews will be working on Berlin Cross Keys Road on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:00 p.m., and 8:00 p.m. to 5:00 a.m. There will be a partial southbound road closure between Watsontown-New Freedom Road in Winslow Township and Turnersville Road in Pine Hill. 

Runnemede

Crews will be working on Evesham Road on Monday, November 16, to Friday, November 20, from 6:30 p.m. to 6:00 a.m. (Monday to Wednesday) and 7:00 a.m. to 3:00 p.m. (Tuesday to Friday) There will be a full road closure between Black Horse Pike in Gloucester Township and West Clements Bridge Road (Route 41) in Runnemede.

Somerdale

New Jersey American Water will be working on 103 East Somerdale Road, on Tuesday, November 17, from 9:00 a.m. to 3:00 p.m. There will be a full road closure between North Browning Avenue and Chestnut Avenue. 

Voorhees

Crews will be working on Evesham Road on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:30 p.m. There will be partial road closures between Haddonfield-Berlin Road in Cherry Hill and Burnt Mill Road in Voorhees.

Winslow

Crews will be working on Berlin Cross Keys Road on Monday, November 16, to Friday, November 20, from 7:00 a.m. to 3:00 p.m., and 8:00 p.m. to 5:00 a.m. There will be a partial southbound road closure between Watsontown-New Freedom Road in Winslow Township and Turnersville Road in Pine Hill. 

The Camden County Department of Public Works is responsible for maintaining over 1,200 miles of county roadway, over 200 bridges and several dams. They are dedicated to making our area safer for motorists and pedestrians through county highway construction projects and road maintenance, including pothole repairs, street sweeping, grass cutting and storm drainage upkeep. The Public Works Department is located in Lindenwold where personnel are on call 24 hours a day, 7 days a week to serve the residents of Camden County.

To report concerns on Camden County roadways, call (856) 566-2980 or visit www.camdencounty.com.